Residential Civil Engineering & Groundworks Case Study for  Strata Homes, Bilborough, Nottingham

Strata Homes

Bilborough, Nottingham

Highlights


Challenges

  • Traces of asbestos discovered during site investigation


Solution

  • Implemented a remediation strategy involving excavation, hazardous material disposal, and clean capping layer installation

  • Conducted third-party validation to ensure successful remediation

  • Demonstrated commitment to high-quality results in production, commercial, and customer care aspects

  • Installed foul and storm pumping station and Carlow tank to handle specialised infrastructure components


Results


  • Ranked as the top-performing contractor throughout Strata Homes' supply chain

  • Successfully completed the project, delivering 120 plots over a 2.5-year contract duration

  • Installed 3970m² of S38 roads and 1105m² of S104 drainage

  • Installed foul and storm pumping station and Carlow tank