Residential Civil Engineering & Groundworks Case Study for  Bellway Homes, Mallard Walk, Staffordshire

Bellway Homes

Mallard Walk, Stafford

Highlights


Challenges

  • Managing large-scale earthworks for attenuation pond

  • Executing complex bridge and culvert works to maintain existing watercourses

  • Addressing waterlogged and damaged areas of the site


Solution

  • Implemented large-scale earthworks for a new attenuation pond

  • Carried out specialised bridge and culvert works

  • Applied soil stabilisation techniques to create a durable, loadbearing haul road in waterlogged areas

  • Constructed 8,500m² of new Section 38 highway, including adoptable and private drainage


Results


  • Delivered infrastructure for 170 new 3-5 bed homes

  • Successfully installed 8,500m² of new Section 38 highway

  • Completed attenuation pond, enhancing site drainage

  • Created a stable haul road in previously waterlogged areas