Bellway Homes
Holbrook Park, Snelsmoor
Highlights
Challenges
Areas with high water table, requiring ground dewatering for pond installation
Designing and constructing a pond liner to prevent water infiltration
Solution
Used a full suite of ground dewatering techniques to remove water from the ground
Collaborated with the client and their consultants to incorporate a 300mm cement stabilised layer into the pond design
Worked closely with the client on a monthly programme, tailoring labour to meet deadlines
Used geogrid installation and bentonite pond liner to address high water table issues
Results
Successfully installed the 23,000 cubic meters pond and delivered 167 plots over a 3.5-year contract duration
Met the client's expectations through collaborative problem-solving and regular quality control
Installed 4341m² of S38 roads and 3317m² of S104 drainage
Provided staged handover documents for superstructure works and before CML dates to ensure quality and customer satisfaction
Installed S278 works, including the formation of a new roundabout under full road closure - 3858m²
Awarded repeat work due to excellent working relationship with the client